12.                   CONCLUSION AND RECOMMENDATION

12.1                    Conclusions

12.1.1               1-hour TSP impact monitoring was carried out in the reporting month. No Action / Limit Level exceedance at AM1 and AM2 was recorded during the period.

12.1.2               Construction noise monitoring was carried out in the reporting month. No Action / Limit Level exceedance at CM1, CM2 and CM3 was recorded during the period.

12.1.3               No Action and Limit Level exceedance was recorded for water quality at M1, M2 and M3 in the reporting month.

12.1.4               Ardeid night roost monitoring was carried out in the reporting month. Two active ardeid night roost areas (ANR1 and ANR2) were observed within the Survey Area. These roosts were located at the mangrove strips in the east and northeast portions of the Project boundary. No Action / Limit Level exceedance at NMS1 and NMS2 was recorded during the period.

12.1.5               Ecological bird monitoring was carried out in the reporting month. Two exceedances in Action Level were recorded during this period’s monitoring of birds including significant declines in point count method result for species diversity of species with conservation importance; and transect walk method result for species diversity of all avifauna species in the community. However, the exceedances were not project-related.

12.1.6               Four environmental site inspections were carried out in the reporting month. Recommendations on mitigation measures for Permit/ Licenses were given to the Contractor for remediating the deficiencies identified during the site inspections.

12.1.7               Four landscape and visual site audits were carried out in the reporting month. Recommendations on mitigation measures for Permit/ Licenses were given to the Contractor for remediating the deficiencies identified during the site inspections.

12.1.8               No environmental complaint, notification of summons and successful prosecution was recorded in the reporting month.


 

12.2                  Comment and Recommendations

12.2.1               The recommended environmental mitigation measures, as proposed in the EIA report and EM&A Manual shall be effectively implemented to minimize the potential environmental impacts from the Project. The EM&A programme would effectively monitor the environmental impacts generated from the construction activities and ensure the proper implementation of mitigation measures.

12.2.2               According to the environmental site inspections performed in the reporting month, the following recommendations were provided:

 

Air Quality Impact

·        The Contractor is recommended to increase watering for haul roads.

Construction Noise Impact

·        The Contractor is reminded to maintain and reinstate the Sound Proof Canvas properly at the western site boundary near Sludge Digestion Tank (SDT).

·        The Contractor is reminded to maintain and reinstate the silentup and sound proof canvas at the western site boundary.

Water Quality Impact

·        No specific observation was identified in the reporting month.

Chemical Waste and Construction Waste Management

·        No specific observation was identified in the reporting month.

Land Contamination

·        No specific observation was identified in the reporting month.

Ecological Impact

·        No specific observation was identified in the reporting month.

Landscape and Visual Impact

·        Please pay extra caution when operating heavy machinery near trees.

Hazard to Life

·        No specific observation was identified in the reporting month.

Permit/ Licenses

·        No specific observation was identified in the reporting month.