8.
SITE
INSPECTION AND AUDIT
8.1.1
Site audits were
carried out by ET on weekly basis at least once per week to monitor the
implementation of proper environmental management practices and mitigation
measures in the Project site.
8.1.2
In the reporting
month, four site inspections were carried out on 5, 13, 21 and 28 December 2022.
8.1.3
No outstanding
issues were reported during the reporting month. The ET Leader’s Site
Environmental Audit are summarized in Appendix M.
8.2
Advice on the Solid and Liquid Waste Management Status
8.2.1
The Contractor
registered as a chemical waste producer for the Contract. Sufficient
numbers of receptacles were available for general refuse collection and
sorting.
8.2.2
The management of waste
generated by the construction is presented in Table 8.1.
8.2.3
The monthly summary
of waste flow table is detailed in Appendix I.
8.2.4
If off-site
disposal is required, the excavated marine mud from the land-based works shall
be disposed of at the designated disposal sites within Hong Kong as allocated
by the Marine Fill Committee or other locations as agreed by the Director. The
Contractor shall ensure no spilling and overflowing of materials during loading
/ unloading / transportation is allowed.
8.2.5
The Contractor was
reminded that chemical waste should be properly handled temporarily in
designated chemical waste storage area on site in accordance with the Code of
Practice on the Packing, Labelling and Storage of Chemical Waste.