11.     FUTURE KEY ISSUES

11.1       Construction Programme for the Next Three Month

·             Demolition of Admin. Building, Sludge Holding Tanks no. 2, Air Floatation Thickener (remaining Bay 9) and RAS by silent method;

·             ELS work and RC structure at IW & PST;

·             Installation of Sheet pile at TTB;

·             Installation of 813mm pipe pile at North, West and East of AGS;

·             Construction of CLP Substation;

·             Excavation of temp. trench for laying power cables and cable draw pits near YLSTP’s entrance;

·             Ground investigation at SDB, SDT & STB;

·             Sheet piling work around Sludge digester no. 1 – 3;

·             Installation of brand drain at Biogas Holder no. 1;

·             Installation of concrete blocks and soil Surcharge at Biogas Holder no. 1;

·             Construction of temp. traffic road at north of SHT no. 3 & 4;

·             Environmental Drill Holes at AFT;

·             Installation of sheet pile at AFT; and

·             Construction of temp. traffic road between AGS & PST through PST no.4.

11.2      Key Issues for the Coming Month

11.2.1     Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3      Monitoring Schedules for the next three months

11.3.1     The tentative schedule for environmental monitoring in the next three months is provided in Appendix E.