12. CONCLUSION AND RECOMMENDATION
12.1 Conclusions
12.1.1 1-hour TSP impact
monitoring was carried out in the reporting month. No Action / Limit Level
exceedance at AM1 and AM2 was recorded during the period.
12.1.2 Construction noise
monitoring was carried out in the reporting month. No Action / Limit Level
exceedance at CM1, CM2 and CM3 was recorded during the period.
12.1.3 No Action and Limit
Level exceedance was recorded for water quality at M1, M2 and M3 in the
reporting month.
12.1.4 Ardeid night roost
monitoring was carried out in the reporting month. Two active ardeid night
roost areas (ANR1 and ANR2) were observed within the Survey Area. These roosts
were located at the mangrove strips in the east and northeast portions of the
Project boundary. No Action / Limit Level exceedance at NMS1 and NMS2 was
recorded during the period.
12.1.5 Ecological bird
monitoring was carried out in the reporting month. No Action / Limit Level
exceedance was recorded for the ecological monitoring of birds on this period.
12.1.6 Four environmental site
inspections were carried out in the reporting month. Recommendations on
mitigation measures for Permit/ Licenses were given to the Contractor for
remediating the deficiencies identified during the site inspections.
12.1.7 Four landscape and
visual site audits were carried out in the reporting month. Recommendations on
mitigation measures for Permit/ Licenses were given to the Contractor for
remediating the deficiencies identified during the site inspections.
12.1.8 No environmental
complaint, notification of summons and successful prosecution was recorded in
the reporting month.
12.2 Comment
and Recommendations
12.2.1 The recommended environmental
mitigation measures, as proposed in the EIA report and EM&A Manual shall be
effectively implemented to minimize the potential environmental impacts from
the Project. The EM&A programme would effectively monitor the environmental
impacts generated from the construction activities and ensure the proper
implementation of mitigation measures.
12.2.2 According to the
environmental site inspections performed in the reporting month, the following
recommendations were provided:
Air Quality Impact
·
The Contractor is reminded to increase watering for dust suppression at
haul roads.
·
The Contractor is reminded to increase watering for dust suppression
during the demolition of S.A.S. Thickener House.
Construction Noise Impact
·
No specific observation was identified in the reporting month.
Water Quality Impact
·
No specific observation was identified in the reporting month.
Chemical Waste and Construction Waste Management
·
The Contractor is reminded to clean up the oil stain on road with chemical
absorbent pad and treat it as chemical waste for disposal.
Land Contamination
·
No specific observation was identified in the reporting month.
Ecological Impact
·
No specific observation was identified in the reporting month.
Landscape and Visual Impact
·
No specific observation was identified in the reporting month.
Hazard to Life
·
No specific observation was identified in the reporting month.
Permit/ Licenses
·
No specific observation was identified in the reporting month.