11.1 Construction
Programme for the Next Three Month
·
Demolition
of Admin. Building, Settled Sewage Overflow Chamber, Sludge Holding
Tanks no. 1, 3 & 4 (below ground), Return Activated Sludge Screw Pump
Pumping station, Air Floatation Thickener and Auxiliary Pumping Station (below
ground);
·
Pipe Laying
and construction of RC chamber at Zone 2B and subsequence diversion work;
·
Sheet pile
installation, ELS work and RC structure at IW & PST;
·
Piling
work at PST & Transformer House;
·
Piling
work at Sludge Thickening Building;
·
Drilling
and installation of dewatering well and observation well at IW & PST;
·
ELS works
at IW & PST;
·
Construction
of RC structure at 3 zone (Location D -Temp.
Primary Sludge Pumping Station);
·
Pipe laying
for Zone 3 diversion;
·
Drilling &
installation of pipe pile wall for demolition of Aeration Tank no. 5-8 at AGS;
·
Construction
of CLP Substation;
·
Construction of MiC office;
·
Demolition of PST no. 4;
·
Ground
investigation at SDB, SDT & STB;
·
Sheet
piling work around Sludge digester no. 1 – 3;
·
Installation
of brand drain at Biogas Holder no. 1;
·
Installation
of concrete blocks and soil Surcharge at
Biogas Holder no. 1;
·
Construction
of temp. traffic road at north of SHT no. 3
& 4;
·
Construction
of PST structure; and
·
Zone
3:
11.2 Key Issues for the Coming
Month
11.2.1 Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, waste management, ecology, land
contamination and landscape and visual impact issues.
11.3 Monitoring
Schedules for the next three months
11.3.1 The tentative schedule
for environmental monitoring in the next three months is provided in Appendix
E.