11.     FUTURE KEY ISSUES

11.1       Construction Programme for the Next Three Month

·             Demolition of FST no. 5, Settled Sewage Overflow Chamber, Sludge Holding Tanks no. 3 & 4 (below ground), Return Activated Sludge Screw Pump Pumping station, Air Floatation Thickener and Auxiliary Pumping Station;

·             Pipe Laying and construction of RC chamber at Zone 2B and subsequence diversion work;

·             Sheet pile installation, excavation work and RC structure at IW & PST;

·             Piling work at PST & Transformer House;

·             Drilling and installation of dewatering well and observation well at IW & PST;

·             ELS works at IW & PST;

·             Sheet pile installation and construction of RC structure at 3 zone (Location D -Temp. Primary Sludge Pumping Station);

·             Pipe laying for Zone 3 diversion;

·             Drilling & installation of pipe pile wall for demolition of Aeration Tank no. 5-8 at AGS;

·             Construction of CLP Substation;

·             Demolition of PST no. 4;

·             Ground investigation at SDT & STB;

·             Construction of PST structure; and

·             Zone 3

    1. E&M work at temp. Gravity thickening tank (Atal);
    2. E&M work at temp. Sludge Holding Tank (Atal);
    3. E&M work at temp. water heater house (Atal);
    4. Sheet pile & RC work at temp. Primary sludge pumping station;
    5. ELS & RC construction at Temp. digested sludge pump;
    6. E&M work at Digested Sludge Pumping Station.

 

11.2      Key Issues for the Coming Month

11.2.1     Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3      Monitoring Schedules for the Next Three Month

11.3.1     The tentative schedule for environmental monitoring in the coming three month is provided in Appendix E.