11.1 Construction
Programme for the Next Three Month
·
Demolition
of FST no. 5, Settled Sewage Overflow Chamber, Sludge Holding Tanks no. 3 &
4 (below ground), Return Activated Sludge Screw Pump Pumping station, Air
Floatation Thickener and Auxiliary Pumping Station;
·
Pipe
Laying and construction of RC chamber at Zone 2B and subsequence diversion
work;
·
Sheet
pile installation, excavation work and RC structure at IW & PST;
·
Piling
work at PST & Transformer House;
·
Drilling
and installation of dewatering well and observation well at IW & PST;
·
ELS
works at IW & PST;
·
Sheet
pile installation and construction of RC structure at 3 zone (Location D -Temp.
Primary Sludge Pumping Station);
·
Pipe
laying for Zone 3 diversion;
·
Drilling
& installation of pipe pile wall for demolition of Aeration Tank no. 5-8 at
AGS;
·
Construction
of CLP Substation;
·
Demolition
of PST no. 4;
·
Ground
investigation at SDT & STB;
·
Construction
of PST structure; and
·
Zone
3
11.2 Key Issues for the Coming
Month
11.2.1 Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, waste management, ecology, land
contamination and landscape and visual impact issues.
11.3 Monitoring
Schedules for the Next Three Month
11.3.1 The tentative schedule
for environmental monitoring in the coming three month is provided in Appendix
E.