8. SITE
INSPECTION AND AUDIT
8.1.1 Site audits were
carried out by ET on weekly basis to monitor the implementation of proper
environmental management practices and mitigation measures in the Project site.
8.1.2 In the reporting month,
four site inspections were carried out on 8, 13, 22 and 29 December
2021.
8.1.3 No outstanding issues
were reported during the reporting month. The ET Leader’s Site Environmental
Audit are summarized in Appendix M.
8.2 Advice
on the Solid and Liquid Waste Management Status
8.2.1 The Contractor
registered as a chemical waste producer for the Contract. Sufficient
numbers of receptacles were available for general refuse collection and
sorting.
8.2.2 The management of waste
generated by the construction is presented in Table 8.1.
8.2.3 The monthly summary of
waste flow table is detailed in Appendix I.
8.2.4 If off-site disposal is
required, the excavated marine mud from the land-based works shall be disposed
of at the designated disposal sites within Hong Kong as allocated by the Marine
Fill Committee or other locations as agreed by the Director. The Contractor
shall ensure no spilling and overflowing of materials during loading /
unloading / transportation is allowed.
8.2.5 The Contractor was
reminded that chemical waste should be properly treated and stored temporarily
in designated chemical waste storage area on site in accordance with the Code
of Practice on the Packing, Labelling and Storage of Chemical Waste.