1.                           INTRODUCTION

1.1                          Background

1.1.1                   The existing Yuen Long Sewage Treatment Works (YLSTW) is a secondary sewage treatment works, located at Yuen Long Industrial Estate serves Yuen Long Town, Yuen Long Industrial Estate and Kam Tin areas with a design capacity of 70,000 m³ per day. Based on the latest planning data, the volume of sewage generation from the YLSTW catchment is estimated to increase to 150,000 m³ per day after 20 years. In addition, since YLSTW has been operating for over 30 years and most of its facilities are of out-dated design and reaching the end of their design life, the environmental facilities of the plant will also be upgraded and hence improving the adjacent environment through upgrading the YLSTW to Yuen Long Effluent Polishing Plant (YLEPP). The Location of Proposed Yuen Long Effluent Polishing Plant is given in Figure 1.

1.1.2                   YLSTW will be reconstructed in two stages to increase its capacity to 150,000 m³ per day. The proposed works, as Stage 1 of the project, will firstly increase the treatment capacity to 100,000 m³ per day. In the course of Stage 1 construction, about half of the existing facilities of YLSTW would be demolished, while the other half would be kept in operation to maintain the sewage treatment service for Yuen Long area.

1.1.3                   The Project is a designated project under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) for which Environmental Impact Assessment (EIA) report and Environmental Monitoring and Audit (EM&A) Manual was approved by EPD (Register No.: AEIAR-220/2019) on 25 April 2019. The Environmental Permit (EP) (EP No. EP-565/2019) was issued by EPD on 26 April 2019.

1.1.4                   Fugro Technical Services Limited (FTS) has been appointed as the Environmental Team (ET) by Drainage Services Department (DSD) to undertake the Environmental Team services for the Project and implement the EM&A works under the Contract No. DC/2019/10 Yuen Long Effluent Polishing Plant -Main Works for Stage 1 (hereinafter referred as “the Contract”).

1.1.5                   This is the 8th Monthly EM&A report to document the findings of site inspection activities and EM&A programme for this project from 1 November 2021 to 30 November 2021 (reporting period) and is submitted to fulfil Condition 3.4 of the EP and Section 12.4.1 of the EM&A Manual. According to Condition 4 of the EP, electronic reporting is provided on the internet website to facilitate public inspection of the report.


 

1.2                        Project Organization

1.2.1                   The Project Organization structure is shown in Appendix B. The key personnel contact names and numbers are summarized in Table 1.1.

1.3                        Construction Programme and Activities

1.3.1                   The construction programme of this project is shown in Appendix A.

1.4                        Works undertaken during the month

1.4.1                   The main construction works carried out in the reporting period were as follow:

·             Site formation works at PST no. 5 & 6;

·             Demolition of FST no. 7 & 8 by crusher excavator;

·             Pre-drill work at PST Stage 1 by 1 rig;

·             Installation of sheet pile at IW;

·             Pile load test at IW;

·             Installation of sheet pile and excavation work at Zone 2A;

·             Construction of RC structure at Zone 3 (Temp. Sludge Holding Tank and Temp. Water Heater Tank);

·             Reinstatement work at Zone 1 diversion area;

·             Overhaul work at Sludge Digestion Tank; and

·             Env. Drill holes at Waste Storage Area.

1.4.2                   The environmental protection and mitigation measures corresponding to the main construction works implemented in the reporting period can be referred to Appendix J.

1.5                        Status of Environmental Licences, Notification and Permits

1.5.1                   A summary of the relevant permits, licenses and/or notifications on environmental protection for this project is presented in Table 1.2.