11.     FUTURE KEY ISSUES

11.1       Construction Programme for the Next Three Month

·        Demolition of FST no. 5-8, Sludge Holding Tanks no. 3 & 4, Auxiliary Pumping Station and Carparks;

·        Construction RC structure for Temp. Thickening tank (Zone 3B);

·        Laying pipes and construction of RC chamber at Zone 2A and subsequence diversion work (nights work);

·        Env. Drill holes at Waste Storage Area;

·        Sheet pile installation at IW & PST;

·        Installation of sheet pile, excavation and construction of temporary chamber at Zone 2B;

·        Construction RC structure at zone 3 (Temp. water heater house and temp. thickening tank);

·        Pipe Laying for Zone 3;

·        Env. Drill holes at Air Floatation Thickener;

·        Installation of sheet pile at Auxiliary Pumping Station;

·        Installation of sheet pile for demolition of Aeration Tank no. 5-8 at AGS;

·        Construction of temp. transformer room (1600A);

·        Construction of Digested Sludge Pumping Station (Zone 3A); and

·        Construction of Temp. Sludge Gravity Thickening Tank (Zone 3B).

11.2      Key Issues for the Coming Month

11.2.1     Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3      Monitoring Schedules for the Next Three Month

11.3.1     The tentative schedule for environmental monitoring in the coming three month is provided in Appendix E.