11.     FUTURE KEY ISSUES

11.1       Construction Programme for the Next Three Month

·        Demolition of FST no. 5-8, & Waste Storage Area, Sludge Holding Tank, carpark, Consolidation Tank & Air Flotation Thickener;

·        Sheet pile installation at IW & PST;

·        Zone 2A, 2B & 3 diversion work;

·        Construction RC structure at zone 3 (Temp. sludge holding tank & Temp. water heater house);

·        Pipe Laying for Zone 3 diversion; and

·        Enviro. GI at workshop & Air Floatation Thickener.

11.2      Key Issues for the Coming Month

11.2.1     Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3      Monitoring Schedules for the Next Three Month

11.3.1     The tentative schedule for environmental monitoring in the coming three month is provided in Appendix E.