11.1 Construction
Programme for the Next Three Month
·
Demolition
of FST no. 5-8 Changing Room & Waste Storage Area;
·
Demolition
of carpark;
·
Sheet pile
installation at IW & PST;
·
Driven
H-pile at IW & PST;
·
Zone 2A,
2B & 3 diversion work; and
·
Enviro. GI
at workshop & Air Floatation Thickener.
11.2 Key Issues for the Coming
Month
11.2.1 Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, waste management, ecology, land
contamination and landscape and visual impact issues.
11.3 Monitoring
Schedules for the Next Three Month
11.3.1 The tentative schedule
for environmental monitoring in the coming three month is provided in Appendix
E.