11.1 Construction Programme for the Next Three
Month
·
Pre-drill work at CLP, Zone 2 & PST no. 8;
·
Demolition of Sludge Holding Tanks no. 3 & 4, Changing room, Waste
Store area, PST no. 5-6 & FST no. 5-8;
·
Demolition of carpark;
·
Sheet pile installation at Inlet Works (IW), Aeration Tank;
·
Driven H-pile at IW & PST;
·
Zone 2 & 3 diversion work including construction temporary tank,
chambers and pipe laying;
·
Removal of sonneratia in Sep & Oct;
·
Installation of instrumentation at Zone 2 & 3;
·
Construction of temporary transformer house; and
·
Construction of 11kV switch gear house and CLP substation.
11.2 Key Issues for the Coming Month
11.2.1 Potential environmental impacts arising from the above
construction activities are mainly associated with construction dust,
construction noise, waste management, ecology, land contamination and landscape
and visual impact issues.
11.3 Monitoring Schedules for the Next Three Month
11.3.1 The tentative schedule for environmental monitoring in the coming
three month is provided in Appendix E.