10.             FUTURE KEY ISSUES

10.1               Construction Programme for the Next Three Month

¡P                 Pre-drill work at Zone 2;

¡P                 Demolition of Sludge Holding Tanks, Detritor 3C & Flow Meter Chamber;

¡P                 Demolition of carpark;

¡P                 Demolition of Final Sedimentation Tanks (FST) no. 7&8;

¡P                 Demolition of Primary Sedimentation Tanks (PST) no. 5&6;

¡P                 Demolition of waste storage area;

¡P                 Sheet pile installation at Aeration Tank, Inlet Works (IW) & Primary Sedimentation Tanks (PST);

¡P                 Driven H-pile at Inlet Works (IW) & Primary Sedimentation Tanks (PST);

¡P                 Zone 2 & 3 diversion work;

¡P                 Enviro. GI at Waste Storage Area & Air Floatation Thickener;

¡P                 Removal of Sonneratia; and

¡P                 Installation of instrumentation at Zone 2 & 3.

10.2               Key Issues for the Coming Month

10.2.1             Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

10.3               Monitoring Schedules for the Next Three Month

10.3.1             The tentative schedule for environmental monitoring in the coming three month is provided in Appendix E.