1.
2.
3.
4.
5.
6.
7.
SITE
INSPECTION AND AUDIT
7.1.1
Site
audits were carried out by ET on weekly basis to monitor the implementation of
proper environmental management practices and mitigation measures in the
Project site.
7.1.2
In
the reporting month, five site inspections were carried out on 2, 8, 16, 23 and
30 June 2021.
7.1.3
No
outstanding issues were reported during the reporting month. Details of
observations recorded during the site inspections are summarized in Appendix
M.
7.2.1
The
Contractor registered as a chemical waste producer for the Contract. Sufficient
numbers of receptacles were available for general refuse collection and
sorting.
7.2.2
The
waste generated by the construction and disposal ground is presented in Table
7.1.
7.2.3
The
monthly summary of waste flow table is detailed in Appendix
I.
7.2.4
If
off-site disposal is required, the excavated marine mud from the land-based
works shall be disposed of at the designated disposal sites within Hong Kong as
allocated by the Marine Fill Committee or other locations as agreed by the
Director. The Contractor shall ensure no spilling and overflowing of materials
during loading / unloading / transportation is allowed.
7.2.5
The
Contractor was reminded that chemical waste containers should be properly
treated and stored temporarily in designated chemical waste storage area on
site in accordance with the Code of Practice on the Packing, Labelling and
Storage of Chemical Waste.