ENVIRONMENTAL
COMPLAINT AND NON-COMPLIANCE
8.1.1
No
Action / Limit Level exceedance was recorded for 1-hr TSP level at AM1 and AM2
in the reporting month.
8.1.2
No
Action / Limit Level exceedance was recorded for construction noise at CM1, CM2
and CM3 in the reporting month.
8.1.3
No
Action and Limit Level exceedance were recorded for water quality at M2 and M3
in the reporting month.
8.1.4
An
Action Level exceedance was recorded for water quality in the reporting month.
The exceedance was recorded at M1 on 10 June 2021. A Limit Level exceedance was
recorded for water quality in the reporting month. The exceedance was recorded
at M1 on 8 June 2021. It was found that these exceedances were not
project-related.
8.1.5
No
Action / Limit exceedance was recorded for noise levels at stations (NMS1 and
NMS2) in close proximity to the active ardeid night roosts.
8.1.6
Two
exceedances in Action Level were recorded for the ecological monitoring of birds
on 15 and 18 June 2021 which included significant declines in species diversity
of all avifauna species (including but not limited to overwintering waterbirds)
in the community; and species diversity of species of conservation importance
only. However, the exceedances were not project-related.
8.2.1
No
environmental complaint, notification of summons and successful prosecution
were received in the reporting month.
8.2.2
Cumulative
complaint log, summaries of complaints, notification of summons and successful
prosecutions are presented in Appendix L.