CONCLUSION AND RECOMMENDATION
7.1.1
No Action and Limit Level exceedance was recorded for air quality
monitoring and construction noise monitoring in the reporting period.
7.1.2
5 Action Level exceedance and 7 Limit Level exceedance were
recorded for water quality in the reporting period. It was found that these
exceedances were not project-related.
7.1.3
No Action / Limit exceedance was recorded for noise levels at
stations (NMS1 and NMS2) in close proximity to the
active ardeid night roosts in the monitoring period.
7.1.4
4 Action Level exceedances were noted for the ecological
monitoring of birds during the reporting period, however, these exceedances
were not project-related.
7.1.5
13 environmental site inspections and 13 landscape and visual site
audits were carried out in the reporting period. Recommendations on mitigation
measures were given to the
Contractor for remediating the deficiencies identified during the site
inspections.
7.1.6
Referring to the Contractor’s information, no environmental
complaint, notification of summons and successful prosecution was received in
the reporting period.
7.1.7
The EM&A methodology has been effective in monitoring the
environmental impacts of the Project and the effectiveness of the mitigation
measures. The data collected were useful in determining whether the Project had
caused unacceptable impacts on the sensitive receivers. Analysis of all
EM&A data collected throughout the baseline and the impact periods
demonstrated the environmental acceptability of the Project.
7.2.1
The recommended environmental mitigation measures, as proposed in
the EIA report and EM&A Manual shall be effectively implemented to minimize
the potential environmental impacts from the Project. The EM&A programme
would effectively monitor the environmental impacts generated from the
construction activities and ensure the proper implementation of mitigation
measures.
7.2.2
According to the environmental site inspections performed in the
reporting period, the following recommendations were provided:
Air Quality Impact
·
No specific observation was identified
in the reporting month. .
Construction Noise Impact
·
The contractor was reminded to
properly maintain the function of the noise barrier.
Water
Quality Impact
·
The contractor was reminded to
properly cover the excavated material and trial trench.
·
Mitigation measures should be provided
to intercept silty runoff from the piling area.
·
Enhance mitigation by providing
sandbags along inner edge of U channel to prevent inflow of silty runoff.
·
Silty deposit on road and in gullies
should be cleaned.
·
Mitigation measures (eg. sandbags / coverings) should be provided to prevent
runoff from the temporary administration building works area flowing out to the
nullah.
·
Mitigation measure (eg. sandbags) should be provided at inlet / outlet of
channel at catchpit to prevent discharge of water.
·
Enhance
the mitigation measure to prevent runoff flowing out to the nullah at area near
temporary administration building.
·
The
contractor was reminded to provide mitigation measure to prevent silt / silty
runoff getting into storm drain and / or checking the existing pipe network for
temporarily sealing up manhole at excavation near piling area.
Chemical
and Waste Management
·
No specific observation was identified
in the reporting month.
Land Contamination
·
No specific observation was identified
in the reporting month.
Landscape and Visual Impact
·
Establish protective barrier for
retain trees T250 & T251.
·
Retain trees T252, T253 – Trench work
within tree protection zone has to be reviewed and
follow specification of works and exercise care when doing Work.
Permit/ Licenses
·
The contractor was reminded to check
availability of the Non-road Mobile Machinery (NRMM) label.[This is the bookmark for