April 2021 |
May 2021 |
June 2021 |
· Overhaul
of Detritor; · Overhaul
of Primary Sedimentation Tank and Final Sedimentation Tank; · Overhaul
of Sludge Holding Tank and Sludge Digestion Tank; · Pre-drill
work by 4 drill rig; · Installation
of instrumentation; · Site
formation work at IW within piling area; · Site
formation works at temporary storage area, admin. Building & work shop; · Erection
of noise barrier; · Erection
of bird curtain; and · Trial pit
for zone 1 diversion work & pre-drill work. |
· Driven
piling work at IW; · Demolition
of Primary Sedimentation Tanks (PST) no. 7 & 8 tanks; · Demolition
of main store; · Demolition
of carpark cover; · Demolition
of workshop; · Sheet
piling; · Construction
of temporary storage area, admin. Building and workshop; · Installation
of sheet piles for Zone 1 diversion; · Pre-drilling
works at Primary Sedimentation Tanks (PST); · Environmental
drill holes inside main store and workshop; · Trench
excavation for UU diversion; and · Breaking
of existing road pavement at Primary Sedimentation Tanks (PST). |
· Pre-drill
work at Primary Sedimentation Tanks (PST) by 2 drill rigs; · Drilling
and install piezometers; · Site
formation works at Primary Sedimentation Tanks (PST); · Breaking
of Primary Sedimentation Tanks (PST) no. 7 & 8; · Sheet pile
installation works for Zone 1 diversion; · Driven
H-pile at Inlet Works (IW) stage 1 by 2 rigs; · Demolition
of main storage by crusher and breaker; · Trial pit
for Zone 2A & 3 diversion; · Construction
of temporary admin. Building, workshop & storage area; · Removal of
sludge from sludge holding tanks; and · Overhaul
work at Final Sedimentation Tanks (FST). |