3.
LANDSCAPE AND
VISUAL
3.1.1
According to the
EM&A Manual, site audits should be undertaken every week during the
construction phase to check that the proposed landscape and visual mitigation
measures are properly implemented and maintained as per their intended
objectives.
3.2.1
According to the
EM&A Manual, site audits should be undertaken every week during the
construction phase to check that the proposed landscape and visual mitigation
measures are properly implemented and maintained as per their intended
objectives.
3.2.2
To monitor and audit the implementation of
landscape and visual mitigation measures, 13 weekly landscape and visual site
audits were carried out in the reporting period. No outstanding issues were
reported during the reporting period. Observations and recommendations during site audits are summarized in Table 4.1.